Nesitu 100MW Solar Hybrid Energy Park & Substation EPC
Nesitu 100MW Solar Hybrid Energy Park & Substation EPC: stage, funding, implementer and location as SSIP records them, with the evidence state of each.
Record
- Stage
- Under Construction
- Location
- Nesitu Industrial Corridor, Eastern Equatoria / Juba Border
- Implementer
- Sinohydro & PowerChina EPC Joint Venture
- Funder
- Ministry of Energy & Dams / African Development Bank (AfDB) Consortium
- Value
- Published value: US$145,000,000
- Source dataset
- commercial.pipeline
Recorded relationships
7 relationships SSIP holds for this entity, each with the evidence state it is permitted to claim. A relationship is not a fact because it is drawn; it is a claim with a source.
Funding
- funds: Ministry of Energy and Dams [ANNOUNCED]
Recorded as investor or sponsor on the pipeline record at stage "Under Construction". Evidence status on the record: VERIFIED. - funds: African Development Bank (AfDB) Consortium [ANNOUNCED]
Recorded as investor or sponsor on the pipeline record at stage "Under Construction". Evidence status on the record: VERIFIED.
Delivery
- implements: Sinohydro & PowerChina EPC Joint Venture [ANNOUNCED]
Recorded as implementing contractor on the pipeline record.
Procurement
- contracting authority for: South Sudan Electricity Corporation (SSEC) [ANNOUNCED]
Recorded as the procurement agency on the pipeline record.
Where
- located in: Central Equatoria [ANNOUNCED]
Pipeline location "Nesitu Industrial Corridor, Eastern Equatoria / Juba Border" names this jurisdiction. - located in: Eastern Equatoria [ANNOUNCED]
Pipeline location "Nesitu Industrial Corridor, Eastern Equatoria / Juba Border" names this jurisdiction.
Sector
- in sector: Power & Energy [ANNOUNCED]
The pipeline record classifies this in "Power & Energy".
Not held
- No infrastructure dependency is recorded for this project.
An absence of records is not a finding of zero.
How to read this
Every figure on this page carries an evidence state — Verified, Operational, Announced, Estimated, Inferred, Disputed, Simulated, Reference or Unavailable — and each state has a stated definition. SSIP does not present an estimate as an observation, and it does not record a missing value as zero.
Read the methodology · Open the evidence ledger · See declared gaps
Related
All projects · Organisations · Knowledge graph · What changed recently
Cite, check and correct
Cite as: “Nesitu 100MW Solar Hybrid Energy Park & Substation EPC”. Strategic Systems Intelligence. https://ssintelligence.online/project/PIP-001. Last updated . Carry the evidence state with any figure you quote.
Methodology · Sources · Corrections — if a record here is wrong, the corrections log is where it is fixed in public.